Clubhouse 1 Project On Schedule

The Clubhouse 1 project remains on budget and on schedule for completion at the end of August. Conference rooms have been upgraded with new kitchenettes, flooring, walls, LED lights and fresh paint. The new billiards room now features its own kitchenette. Restrooms have been retiled, refloored and fitted with new fixtures, stalls and mirrors. The ballroom floors have been refinished, new windows have been installed and a new soundboard is scheduled for installation.

Tentative Timeline

  • September 3: Recreation staff begin the move-in process
  • September 16: A soft reopening will support any troubleshooting while the move-in process continues
  • Pool 1 may reopen earlier
  • A grand reopening event will be held in October (date TBD)

Watch the August 10 “This Day” on the Village YouTube channel featuring Projects Manager Guy West, and stay tuned for future details.