Gate 5 Lane Update

VMS Streets and Sidewalks personnel will start repairing asphalt at Gate 5 on Monday, February 12; the vendor is scheduled to install new lane sensor loops Wednesday, February 14; and the repaired Gate 5 lane is tentatively scheduled to reopen Thursday, February 15.

Thank you for your patience and understanding during this process.